Power outages and POD shutdowns in we... Log Out | Topics | Search
Moderators | Edit Profile

CN Discussion » Scheduled Service Outages » Power outages and POD shutdowns in week January 9th « Previous Next »

Author Message
Top of pagePrevious messageNext messageBottom of page Link to this message

Roger Ehrlich
Username: Rehrlich

Registered: 09-2014
Posted on Sunday, January 08, 2017 - 10:51 pm:   

Hello
We will have a contractor in to perform electrical power installations during the week of January 9th, 2017. It is anticipated that this work will take 5 days. During this time physical PODs will have to be powered off for a few days within this period. Updates will follow.
Cheers, Roger
Top of pagePrevious messageNext messageBottom of page Link to this message

Roger Ehrlich
Username: Rehrlich

Registered: 09-2014
Posted on Tuesday, January 10, 2017 - 01:33 pm:   

Hello
Regarding the electrical power installations in the CN datacenter during the week of January 9th, 2017:

Production servers and virtual labs shall remain up.

One row of racks shall be powered off at a time. Thus physical PODs will not be available during the power outages.

Row A: PODs 2,3,4,5,6,8,9,11
Row B: PODs 10,12,13,14,15,16,17,18,19,20,21,22,23,24

The date and time has yet to be determined. Updates will follow.
Cheers, Roger
Top of pagePrevious messageNext messageBottom of page Link to this message

Roger Ehrlich
Username: Rehrlich

Registered: 09-2014
Posted on Monday, January 16, 2017 - 03:57 pm:   

Hello
Regarding the electrical power installations in the CN datacenter during the weeks of January 9th & 16th, 2017:

Production servers and virtual labs remain up.

Row B: PODs 10,12,13,14,15,16,17,18,19,20,21,22,23,24 are powered off. These Physical PODs will not be available during the power outages today 2017-01-16. These PODs will be powered on tomorrow 2017-01-17.

Updates will follow.
Cheers, Roger
Top of pagePrevious messageNext messageBottom of page Link to this message

Roger Ehrlich
Username: Rehrlich

Registered: 09-2014
Posted on Thursday, January 26, 2017 - 07:57 am:   

Hello
Regarding the electrical power installations in the CN datacenter during January, 2017:

Our apologies, however this project was extended due to contractor availablity and some technical issues faced which are being resolved.

Production servers and virtual labs shall remain up.

Thus physical PODs will not be available during the power outages.

Row A: PODs 2,3,4,5,6,8,9,11 will be powered off today. These Physical PODs will not be available until later next week.

Row B: PODs 10,12,13,14,15,16,17,18,19,20,21,22,23,24
PODs 22 + 23 were brought up last week. PODs 10 + 12 will remain off a little longer for maintenance. The remaining PODs will be back up this Friday or early next week.

Updates will follow.
Cheers, Roger

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action:

Topics | Last Day | Last Week | Tree View | Search | Help/Instructions | Program Credits Administration